Project Description
Client: | Progresif Cellular |
Entity: | ADCB |
Project Name: | Phase X - PMB2 Temporary 12m Mast |
Year: | 2017 |
Overview: | This rapid deployment project involved the design check, fabrication of precast components, supply of ancillary and electrical equipment and installation of a 12m temporary mast cell-site at the industrial island complex (under development) of Pulau Muara Besar. The works were completed within 3 weeks as required by the client. No foundations were needed to be installed as the guyed mast relies on the 3-precast blocks supplied to anchor the mast. |